Learn the secret of effective scope change management

Tags: Leadership, Tom Mochal, change management, Project Management Newsletter

  • Save
  • Print
  • Recommend
  • 13

Takeaway: One of the conflicts project managers face is that they don't want to say no when someone asks for a scope change. Here's a trick that takes away the need to do that.

Project scope refers to the box that defines the work of your project. The boundaries of the box separate the areas your project will be responsible for versus those areas your project will not be responsible for. It provides the baseline against which you can perform scope change management throughout the project.

One of the conflicts project managers face is that they don't want to say no when someone asks for a scope change. Since the requestor is usually a client manager, stakeholder or end user, the project manager usually feels an instinct to do whatever is needed. Saying "no" to the client request means not being client focused, or not satisfying the client's needs.

However, there's a simple way to get you out of this yes/no dilemma. The secret is simply to understand that the project manager doesn't have to be the "no guy." In fact, the project manager doesn't need to decide one way or another.

The project manager's job is to identify scope change requests and take them through the scope change management process. The next time a client asks for a change in scope, ask him to send you an e-mail explaining the new capability and the business value of the change. Have him include a description of the consequences if the change is not made. Determine the impact to the project on terms of budget and schedule and then send the benefits and costs to the sponsor for approval.

If the client insists on the need for the change, explain that you're not disagreeing with him, but it's just not your call. The sponsor makes decisions on scope change requests.

Placing the focus on the sponsor to make scope change decisions changes the entire dynamic of a discussion. It shifts the pressure from the project manager to the client, forcing him to explain the benefits well enough that the sponsor will approve. The project manager can then focus on what he or she should be doing—proactively and effectively executing the scope change management process.

  • Save
  • Print
  • Recommend
  • 13

Print/View all Posts Comments on this article

An excellent tip ! panrio | 04/06/05
Small Business Focus GunnyMike | 04/06/05
Size doesn't matter PMP'sicle | 04/06/05
How to say No to a Small Business spencemeister@... | 04/07/05
Delayed specification changes have a dramatic cost impact eramos@... | 11/03/05
Couldn't agree more chorenf@... | 04/10/05
risk is deflected but not solved viveka | 04/06/05
Uhhhh ... PMP'sicle | 04/06/05
scope change management ortreg@... | 09/14/05
define up front AlbanyPMP | 11/16/05
Of course guillenkma | 12/05/07

What do you think?

White Papers, Webcasts, and Downloads

Article Categories

Security
Security Solutions, IT Locksmith
Networking and Communications
E-mail Administration NetNote, Cisco Routers and Switches
CIO and IT Management
Project Management, CIO Issues, Strategies that Scale
Desktops, Laptops & OS
Windows 2000 Professional, Microsoft Word, Microsoft Excel, Microsoft Access, Windows XP,
Data Management
Oracle, SQL Server
Servers
Windows NT, Linux NetNote, Windows Server 2003
Career Development
Geek Trivia
Software/Web Development
Web Development Zone, Visual Basic, .NET

SmartPlanet

Click Here