Working with repetitive tasks in Microsoft Project
Takeaway: In Microsoft Project, it's common for project plans to focus on repeated task names instead of the resources that you're going to use. This macro will help clear up confusing plans by adding the resource names.
How many times have you gone into a consulting engagement and found a Microsoft Project plan that looked something like Figure A? This kind of formatting is common among software development houses that use an iterative design/build methodology.
| Figure A |
![]() |
While it’s hard to argue with the logic of a plan like this, it’s hardly ideal for finding your way through the project plan once you start applying filters or views that don’t show the full task hierarchy. Figure B shows the same project in the Resource Usage view. This shows how the schedule can become difficult to use once you get resources assigned. As you can see, the same task name shows up multiple times for a resource. It would be very difficult to tell which phase or iteration each task belonged to. Although this view is a great way to see a project broken down by the resources and the tasks to which they are assigned, the naming scheme in this project will just not do.
| Figure B |
![]() |
I’ll show you a Microsoft Project macro you can keep in your toolkit to help you clean up this kind of project plan when you go on-site with a customer.
Option 1: Rename the tasks
The first and most attractive option is to just rename the tasks to include the name of their summary task. The macro in Listing A will look at each task in the project and check to see that the task is not a top-level task and does not have any child tasks of its own. If those conditions are both true, the macro will rename the task to this format: <name of parent task> | <current name of task>. If the task is a top-level task or has subtasks, the name will not be edited. The resulting task names for the example project are shown in Figure C.
| Figure C |
![]() |
The macro explained
Line 100 starts a loop that will iterate through every task in the active project.
Line 110 tests the current task object to make sure it’s not a blank line. A blank line would cause the code on Line 120 to cause an error.
Line 120 tests the current task object to see if it has any subtasks. The number of OutlineChildren is equal to the number of subtasks a task has. Another way to test this would be to test for tskTask.Summary = False, but since we’re working with the OutlineParent and OutlineLevel, I decided to use the OutlineChildren method. This line also tests the task to see what outline level it’s on. The OutlineLevel property of a task is equal to the number of “indentations” it is from the top level. An OutlineLevel of 2 means that a task’s OutlineParent is a top-level task (OutlineLevel = 1).
If the statements on Line 120 are both true, the code on line 130 will edit the task’s Name property to be equal to the name of its OutlineParent and its current name, separated by the pipe character.
Lines 140 and 150 just end their respective If statements.
Line 160 starts the For loop over again if there are more tasks.
One possible reason to edit this macro for your own use is if you need two levels of outline parent’s names in the task name field; you could edit line 130 to look like this:
tskTask.Name = tskTask.OutlineParent.OutlineParent.Name & “ | “ & _
tskTask.OutlineParent.Name & “ | “ & tskTask.Name
This new line will make the task’s name include the name of its parent and its grandparent.
Option 2: Add the new name to a custom field
Some clients won’t want you to rename the tasks. If this is the case, you can easily edit this macro to add the new multilevel name to a custom field instead of to the task’s name field. To do this, just edit Line 130 to something like this:
tskTask.Text20 = tskTask.OutlineParent.Name & " | " & tskTask.Name
Note that instead of tskTask.Name, this line assigns the new name to tskTask.Text20. This new line will place the new name into the Custom field called Text20. You could choose to use any of the 30 text fields for this purpose. Then you could add this custom text field to any view and use it as a reference so that it is clear which “Design” task is being referred to in the view.
Print/View all Posts Comments on this article
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
White Papers, Webcasts, and Downloads
- Why Isn't Server Virtualization Saving Us More? A Few Small Changes May Dramatically Increase Your Efficiency VMware Ever wonder why your company isn't saving more from its server virtualization? Making a few small changes could dramatically increase your efficiency. Download Now
- Security Explorer for SharePoint Version 7.0.2 ScriptLogic Security Explorer for SharePoint is a powerful, graphical solution for ... Download Now
- The True Costs of Virtual Server Solutions VMware Discover ways to streamline and simplify your assessment of the total acquisition costs of a server virtualization environment. Download Now
- Five Steps to Determine When to Virtualize YourServers VMware Thinking of virtualizing the servers at your company? Use this step-by-step guide to determine when's the best time to make your big move. Download Now
- VMware Infrastructure: A Guide to Bottom-Line Benefits VMware Frustrated by the high cost of maintaining or building ever-larger data centers? Get the facts you need to formulate your Virtualization Action Plan. Download Now
Article Categories
- Security
- Security Solutions, IT Locksmith
- Networking and Communications
- E-mail Administration NetNote, Cisco Routers and Switches
- CIO and IT Management
- Project Management, CIO Issues, Strategies that Scale
- Desktops, Laptops & OS
- Windows 2000 Professional, Microsoft Word, Microsoft Excel, Microsoft Access, Windows XP,
- Data Management
- Oracle, SQL Server
- Servers
- Windows NT, Linux NetNote, Windows Server 2003
- Career Development
- Geek Trivia
- Software/Web Development
- Web Development Zone, Visual Basic, .NET